Progress at constructing HPP Brežice

20 Maj, 2014
Progress at constructing HPP Brežice

It is the third month of intensive terrain works at the HPP Brežice construction yard, namely completing the diversion channel and digging construction pits. Of 650,000m3 in total, 380,000m3 of material have already been dug out. The start of diverting the Sava River into the diversion channel is planned for the end of May, the diversion channel will remain operational during the construction of HPP Brežice. The work is being undertaken by the consortium of RGP d.o.o., CGP d.o.o. and Kostak d.d. with local subcontractors. The consortium is in charge of the whole organizational layout of the construction site. The works proceed as planned and within the set financial frame.