The state of works at HPP Brežice

02 Jun, 2015
The state of works at HPP Brežice

The construction works of the production part of HPP Brežice are in full swing and are within the planned timeframe. There are no outstanding problems, therefore we expect a smooth operation in the future, according to the plan. Even more so, as more than 95% of all planned contracts have already been signed with suppliers and providers.
There are approximately 200 workers on the site daily, who manage the works on all segments of the future hydro plant. By the end of May 2015, more than 45,000 m3 of concrete and 3,300 tons of armature have been built into the HPP Brežice facilities. The production and delivery of hydro-mechanic, turbine, generator and electro equipment are in lines with contractual obligations of the providers. First radial gates are undergoing installation into the overflow structure, suction tube cones are being fixed on the overflow parts of the machine facility. The final 7th liner of the access bridge will be completed by the end of June.