Contract for delivery of power transformers

Bogdan Barbič (HESS CEO) and Marko Gabrovšek (C&G d.o.o. CEO) signed a contract for delivery of a power transformer for HPP Brežice and a spare one. The contract was signed at C&G in Ljubljana on 23 July 2014. In the case of malfunction, the spare transformer 117/10.5(6.3)kV will substitute for any of the power transformers in HPP Boštanj, HPP Art-Blanca, HPP Krško, HPP Brežice, HPP Mokrice and HPP Vrhovo. Dimensions of the spare transformer allow for its use at any of the above mentioned locations. It shall be stored at HPP Arto-Blanca.
The power transformer 117/10.5kV is to be installed at HPP Brežice. Its power is 65 MVA and its dimensions fit to all three generators at HPP Brežice.
Tender documentation and the process of public procurement were managed by HSE Invest d.o.o. on behalf of HESS d.o.o. The value of the transformers is set to 1,403,905 EUR (VAT not included). C&G d.o.o. will deliver the transformers in co-operation with their Slovenian subcontractor Kolektor Etra d.o.o.

 

HESS d.o.o.
Pregled zasebnosti

Ta spletna stran uporablja piškotke, tako da vam lahko zagotovimo najboljšo možno uporabniško izkušnjo. Informacije o piškotkih se shranjujejo v vašem brskalniku in opravljajo funkcije, kot je prepoznavanje, ko se vrnete na našo spletno stran, ter pomagajo naši ekipi razumeti, kateri deli spletnega mesta se vam zdijo najbolj zanimivi in koristni.