Milestones

Important milestones of HPP Krško:

  • 6 October 2006
    National detailed site plan is approved for HPP Krško
  • 14 June 2007
    Environmental approval is granted
  • 21 November 2007
    Start of construction
  • 12 June 2012
    Generating unit initial run with running water at HPP Krško
  • 3 July 2012
    Synchronisation of HPP Krško’s first generating unit
  • 7 March 2013
    Technical inspection of the dam structure
  • 1 April 2013
    Start of trial operation of the dam structure
  • 23 May 2013
    Technical inspection of the reservoir
  • 7 June 2013
    Start of trial operation of the reservoir
  • 7 June 2013
    Official opening of HPP Krško and the bypass road
  • 24 March 2014
    Operating licence obtained for the dam structure
  • 1 April 2014
    HPP Krško starts regular operation
  • 23 May 2014
    Operating licence is obtained for the reservoir